Most Ontario building permit fees are a rate times the floor area of the work, with a minimum fee. In 2026 the minimum is $214.79 in Toronto, $244.00 in Mississauga, $291 in Hamilton and $160.00 in Guelph. Finishing a 75 m² basement works out to about $300–$480 in permit fees in these cities. Always confirm the current fee with your municipality.
A building permit in Ontario usually costs a few hundred dollars for a deck, basement or small renovation, and more for an addition or new house. Each municipality sets its own fees, and most charge a rate per square metre or square foot of the work, with a minimum fee. The figures below come from each city's published fee schedule. Fees change, so confirm the current amount with your municipality before you apply.
Building Permit Fees in Ontario (2026)
Toronto (effective January 1, 2026)
| Minimum permit fee | $214.79 | Any permit |
|---|---|---|
| New house or addition | $18.56 per m² | Plus $56.33 per new residential unit |
| Finishing a basement | $6.20 per m² | Basement finishing in a dwelling |
| Interior alterations | $11.53 per m² | Residential floor replacement $13.41 per m² |
| Deck, porch or carport | $214.79 flat | Residential |
| Furnace or HVAC replacement | $214.79 flat | HVAC with air conditioning $270.64 |
Mississauga (2026 schedule)
| Residential minimum | $244.00 | Houses |
|---|---|---|
| New house; residential addition | $18.99 per m²; $13.96 per m² | Detached, semi, town, duplex |
| Finishing a basement | $5.64 per m² | Houses |
| Additional residential unit | $11.33 per m² | Plus the minimum residential fee |
| Deck, porch or basement walkout | $244.00 each | Houses |
Hamilton, Kitchener and Guelph
| Hamilton minimum | $291 | The city page shows no effective year |
|---|---|---|
| Hamilton basement finishing | $4.06 per m² | Also renovating finished areas |
| Hamilton additional dwelling unit | $515 flat | Detached rear-yard unit $1,030 |
| Kitchener basement finishing or interior alterations | $0.37 per sq ft ($95 minimum) | Plus a $250 rebate fee, refunded when the final inspection passes; the page shows no date |
| Kitchener deck, porch or shed | $95 each | Flat |
| Guelph minimum (low-rise residential) | $160.00 | Effective July 1, 2026 |
| Guelph basement finishing or renovations | $0.59 per sq ft | Accessory apartment $0.59 per sq ft, $480.00 minimum |
| Guelph deck, porch, shed or garage | $160.00 flat | Garage per bay |
Example: Permit Fee to Finish a Basement
Calculated from the published rates above for a 75 m² (807 sq ft) basement: Toronto $465.00, Mississauga $423.00, Hamilton $304.50, Kitchener $298.70 plus the $250 refundable rebate fee, and Guelph $476.30. These are our own calculations, not quotes from the cities.
What Affects the Price
- Floor area of the work, since most fees are a rate times the area
- Type of work: new floor space costs more per m² than finishing or altering existing space
- Your municipality and its minimum fee
- Separate flat fees for decks, HVAC, plumbing fixtures or backwater valves
- Refundable deposits such as Kitchener's rebate fee
- Drawings or a designer's fee, which are separate from the permit fee
- Development charges when you add a new unit
What Requires a Building Permit in Ontario?
A permit is usually needed for structural changes, finishing a basement, most decks more than 24 inches (600 mm) off the ground, new or moved plumbing, new heating equipment, additions and second units. Painting, flooring and like-for-like fixture swaps usually do not need one. Small sheds and low decks are often exempt, but the size limits depend on the Ontario Building Code and local by-laws, so check with your building department before you build.
Electrical work is separate. It goes through an Electrical Safety Authority (ESA) notification, not a building permit, and has its own fee.
How Long Permits Take, and Building Without One
Review times depend on the municipality, the type of project and whether the application is complete, so ask your building department for its current timelines. Building without a required permit can lead to an order to stop work, open up finished walls for inspection or remove the work, and it can cause problems when you sell or make an insurance claim. To get a permit after the fact, apply as normal; the city may ask for drawings and for parts of the work to be exposed so an inspector can see them.
Getting Quotes
Ask contractors whether their price includes applying for the permit, preparing drawings and booking inspections, or whether you are expected to handle them. The fee itself is paid to the city and is the same whoever applies.
Planning a project that needs a permit? Request quotes through Pro Tasker and compare independent local contractors.
Common questions
How much is a building permit in Ontario?
It depends on the city and the size of the work. In 2026 minimum fees are $214.79 in Toronto, $244.00 in Mississauga, $291 in Hamilton and $160.00 in Guelph, and larger projects are charged per m² or sq ft. Confirm the current fee with your municipality.
What are the City of Toronto building permit fees?
Toronto's 2026 schedule has a $214.79 minimum, $18.56 per m² for a new house or addition, $6.20 per m² for finishing a basement, $11.53 per m² for interior alterations and a flat $214.79 for a residential deck or porch.
How much does a basement permit cost?
Finishing a 75 m² basement works out to about $300–$480 in permit fees in Toronto, Mississauga, Hamilton, Kitchener and Guelph, based on their published rates. Kitchener also takes a $250 refundable rebate fee.
How much does a deck permit cost?
Several cities charge a flat fee: $214.79 in Toronto, $244.00 in Mississauga, $95 in Kitchener and $160.00 in Guelph. Hamilton charges $5.36 per m² of deck.
Is an ESA permit the same as a building permit?
No. Electrical work in Ontario is filed with the Electrical Safety Authority through a separate notification with its own fee. A renovation can need both.
Keep reading
- Building Permit Services: costs, what the work involves and quotes
- Which Home Renovations Need a Permit in Ontario? (Complete 2026 Guide)
- Do You Need a Permit to Finish a Basement in Ontario?
- Do You Need a Building Permit for a Deck in Ontario? (2026)
- Do You Need a Permit for a Bathroom Renovation in Ontario? (2026)