Get bathroom renovation quotesA bathroom renovation in Ontario takes 1–4 weeks depending on scope. A cosmetic refresh (new paint, fixtures, vanity) takes 3–7 days. A full gut renovation involving new tile, plumbing changes, and a new shower takes 3–5 weeks once work begins — plus 1–4 weeks of planning and permit time before work starts.
Bathroom Renovation Timeline by Project Type
| Cosmetic refresh (paint, hardware, vanity) | 3 – 7 days | No permit required; quick turnaround |
|---|---|---|
| Mid-range reno (new tile, tub, fixtures) | 1.5 – 3 weeks | Tile work is the main time driver |
| Full gut reno (everything replaced) | 3 – 5 weeks | Including plumbing rough-in and tile |
| Full reno with layout change | 4 – 7 weeks | Moving drains requires permit + inspection wait |
| Planning + permit (add before above) | 1 – 4 weeks | Design decisions, materials ordering, permit approval |
Week-by-Week Full Gut Bathroom Renovation Schedule
- Week 1: Demolition — remove old tile, vanity, toilet, tub/shower. Inspect for water damage. Rough-in inspection if plumbing is moving.
- Week 2: Rough-in work — plumber relocates drain/supply if needed; electrician adds circuits; building inspection.
- Week 3: Waterproofing, cement board, tiling begins. Tile work takes 3–5 days.
- Week 4: Tile grouting and curing, vanity and toilet installation, fixture installation.
- Week 5: Touch-ups, paint, accessories, final inspection if permitted.
What Causes Bathroom Renovation Delays?
- Backordered tiles or fixtures — popular tiles can have 4–8 week lead times; order materials before work begins
- Permit and inspection wait times — municipal inspections can have 3–10 business day wait
- Hidden water damage discovered during demolition — adds 3–7 days for repair and drying
- Contractor scheduling — good Ontario contractors are booked 2–6 weeks out