What Should a Home Renovation Contract Include in Ontario? (2026)

A verbal agreement with a contractor is worth nothing in Ontario. Here's exactly what your written renovation contract must include before you pay a deposit.

Need a contractor? Compare quotes from independent local contractors.

Get a quote

In Ontario, any home renovation over $50 requires a written contract under the Consumer Protection Act if it involves a direct agreement (door-to-door or solicited at home). For any project over $1,000, always insist on a written contract regardless. Here's what it must contain.

12 Essential Clauses in Every Ontario Renovation Contract

  1. Full contractor information: legal business name, address, phone, HST number, WSIB account number
  2. Full homeowner information: your name, property address
  3. Detailed scope of work: every task, every room, every material — no vague language
  4. Material specifications: brand, model, colour, grade — not just "tile" or "paint"
  5. Start date and estimated completion date
  6. Total price including HST — or the hourly rate with an estimated total
  7. Payment schedule: deposit amount, milestone payments, holdback at completion
  8. Change order process: written approval required before any additional work or charges
  9. Permit responsibility: who applies, who pays, who is on site for inspections
  10. Subcontractor disclosure: who they are and confirmation they're insured
  11. Warranty terms: what's covered, for how long, and how to make a claim
  12. Dispute resolution: what happens if there's a disagreement (lien rights, arbitration, Small Claims)

Serving 30 Ontario cities

Get a quote

About a minute · No account needed

Add email or job details (optional)

Sent to up to 3 checked, independent contractors in your area. Pro Tasker does not do the work itself.

The Holdback Clause — Protect Yourself at the End

Ontario's Construction Act gives contractors the right to place a lien on your property if they're not paid. Protect yourself by including a 10% holdback clause — withhold 10% of the total contract value until 45 days after substantial completion. This is the statutory holdback under Ontario law.

Change Orders: The Most Important Clause

Most renovation disputes in Ontario come from verbal "sure, we can do that too" conversations that turn into unexpected invoices. Your contract must state clearly that no additional work will be performed without a written, signed change order specifying the additional cost and timeline impact.

Red Flags in a Renovation Contract

  • No HST number — every registered business must have one
  • Vague scope ("renovate kitchen") with no itemization
  • No defined payment milestones — just "50% upfront, 50% when done"
  • No permit responsibility clause
  • No warranty language — or "satisfaction guaranteed" with no specifics
  • No dispute resolution clause
  • Contractor cannot explain any clause when asked

What to Do If a Contractor Won't Provide a Written Contract

Walk away. A contractor who won't put the agreement in writing is either inexperienced, hiding something, or planning to dispute your expectations later. In Ontario, the courts will not enforce verbal agreements in most home renovation disputes.

Serving 30 Ontario cities

Ready for quotes?

About a minute · No account needed

Add email or job details (optional)

Sent to up to 3 checked, independent contractors in your area. Pro Tasker does not do the work itself.

Keep reading