Get ev charger installation quotesA standard Level 2 EV charger installation in Ontario takes 2–4 hours for an ESA-certified electrician. This includes running the circuit from your electrical panel, mounting the charger unit, and completing the ESA inspection. If your panel needs an upgrade first, add 4–8 hours (sometimes scheduled as a separate day).
EV Charger Installation Timeline by Scenario
| Simple install (panel has capacity, short run) | 2 – 3 hours | Garage next to panel, no obstacles |
|---|---|---|
| Standard install (moderate wire run) | 3 – 4 hours | Most Ontario detached homes |
| Complex install (long wire run, conduit) | 4 – 6 hours | Detached garage, finished basement routing |
| Panel upgrade required (added separately) | +4 – 8 hours | Often scheduled as separate visit |
| ESA permit inspection | 1 – 5 business days | After installation; required before use |
What Happens During EV Charger Installation in Ontario
- Electrician assesses panel capacity and identifies optimal circuit location
- Dedicated 240V circuit (40–60 amp) is run from the panel to the charger location
- Conduit is installed where required (exposed runs in garage, exterior)
- Charger unit is mounted and wired
- Circuit is tested and charger is commissioned
- ESA permit is applied for — inspector visits within 1–5 business days to sign off
Does EV Charger Installation Require a Permit in Ontario?
Yes — any new 240V circuit installation in Ontario requires an ESA (Electrical Safety Authority) permit. The permit is pulled by the licensed electrician and is included in most professional installation quotes. You cannot legally use the charger until the ESA inspector signs off. The inspection is typically scheduled within 1–5 business days after installation and takes 15–30 minutes.
Keep reading
- EV Charger Installation: costs, what the work involves and quotes
- EV Charger Rebates in Ontario 2026: What Is Still Available
- Level 2 vs Level 1 EV Charger: Which Do You Need in Ontario?
- EV Charger Installation Cost in Ontario 2026
- Level 2 EV Charger Installation in Ontario — Complete Homeowner Guide 2026